Testing and commissioning turn an installation into a proven, documented, operable system. The work is only as valuable as its evidence: what was tested, how, with which instrument, against which criterion, by whom — and what happened to every failure.
What this department covers
- Planning: ITPs, method statements and hold points
- Test safety
- Core electrical tests and what they reveal
- Protection and functional testing
- Energisation
- Records and handover
- Troubleshooting test results
01The commissioning lifecycle
Commissioning is a sequence of controlled stages. Each stage depends on the evidence of the previous one, and hold points prevent the next step until results are reviewed and accepted by the responsible parties.
| Document | Content | Owner |
|---|---|---|
| Inspection & Test Plan (ITP) | Every inspection/test, reference document, acceptance criteria, record form, H/W/R points | Contractor, approved by consultant/client |
| Method statement & risk assessment | How each test is performed safely: isolation, barriers, equipment, competence | Contractor |
| Test sheets / forms | Blank records with fields for instrument, calibration, readings, result, signatures | Contractor (client forms where mandatory) |
| Energisation / switching programme | Step-by-step switching, responsibilities, communications | Authorised person / network operator |
| Commissioning schedule | Sequence and dependencies across disciplines | Commissioning manager |
02Test safety
Many tests involve high test voltages, stored energy or proximity to live equipment. Testing is controlled work: under the site's permit or safety-document system, with defined test areas, barriers and signage, competent and authorised personnel, calibrated instruments in good condition, and — critically — discharge and earthing of the equipment under test after every insulation or withstand test.
Long cables and large windings store charge after insulation or withstand tests. Discharge and earth them through approved means for at least as long as the instrument and procedure require before touching connections.
03Core electrical tests
| Test | Measures | Reveals | Notes |
|---|---|---|---|
| Visual & mechanical inspection | Conformity with drawings and workmanship | Damage, wrong materials, missing parts, poor terminations | Done first; often the most productive check |
| Continuity of protective conductors | Resistance of CPCs and bonds | Broken or high-resistance earth paths | Low-resistance ohmmeter |
| Insulation resistance (IR) | Resistance under DC test voltage | Moisture, contamination, damage | Test voltage per equipment and standard; temperature affects readings |
| Polarisation index / DAR | Ratio of IR at two times | Moisture/contamination trends in windings | Interpret with equipment-specific guidance |
| Polarity & phase sequence | Correct connections | Reversed L–N, wrong rotation | Before connecting motors and three-phase loads |
| Earth-fault loop impedance | Impedance of the fault path | Whether protection will disconnect in time | Compare with device maximums |
| RCD tests | Trip current and time | RCD function | Per applicable regulations |
| Ratio, winding resistance, vector group | Transformer/CT characteristics | Internal faults, wrong taps or connections | Compare with factory results |
| Withstand / VLF / partial discharge (MV) | Insulation under elevated AC stress | Installation defects in cables and accessories | As specified by project and manufacturer |
Acceptance criteria are not universal. A test sheet that says only "OK" is not evidence. Record the actual value, the criterion it was compared with, and the source of that criterion (manufacturer data, specification clause or standard referenced by the project).
04Protection, control and functional testing
Once static tests are complete, functional testing proves that systems behave as designed: protection relays operate at their settings and trip the right breakers; interlocks prevent prohibited operations; control circuits, indications and alarms work; changeover and transfer schemes perform their sequence; and signals reach the SCADA or BMS correctly. These tests are often performed with control supplies energised but main circuits isolated.
| System | Functional test |
|---|---|
| Protection | Secondary injection of each function; trip matrix to breakers; trip circuit supervision |
| Interlocks | Each mechanical, key and electrical interlock attempted in prohibited states |
| Changeover / ATS | Mains failure simulation, transfer timing, retransfer and inhibit conditions |
| Motor control | Local/remote, start/stop, E-stop, overload trip, run feedback |
| Instrumentation | Loop checks at 0, 25, 50, 75 and 100 % (or as specified) |
| SCADA/BMS | Point-to-point for every signal; alarm generation and acknowledgement |
05Energisation
Energisation is the most hazardous milestone and is controlled accordingly. It proceeds only after a documented review of all pre-energisation evidence, under an approved switching programme, with the network operator or responsible authorised person in control. After energisation, checks include voltages and phase rotation at each board, phasing before closing any parallel or ring connection, protection stability on load, and thermography after a period of loading.
- Readiness review.All tests complete, results accepted, punch items that affect safety closed, permits cancelled.
- Briefing.Switching programme, roles, communication, emergency arrangements.
- Energise in stages.From source towards loads, checking each stage before proceeding.
- Verify.Voltage, phase rotation, phasing at open points, indications and metering.
- Load and monitor.Gradual loading; on-load protection checks; thermography.
- Record.Energisation certificate, readings, any abnormalities.
06Records and handover
Handover documentation lets the operator run, maintain and later modify the system. Typical contents are as-built drawings, approved settings, test and commissioning records, certificates, O&M manuals, spares and tools lists, warranties, and training records. The Electrical Inspection & Testing Log template provides a register for tracking inspections, results, defects and retests.
07Troubleshooting test results
| Result | Possible causes | Next steps |
|---|---|---|
| Low IR on a new cable | Moisture at ends, damaged sheath, terminations contaminated | Clean/dry terminations; disconnect equipment; test sections; locate fault |
| IR varies widely between tests | Temperature/humidity changes, surface leakage | Record conditions; use guard terminal; retest at stable conditions |
| Winding resistance imbalance | Loose connection, tap changer contact, wrong tap | Check connections and tap position; repeat after tap operation per manufacturer |
| Relay trips at wrong current | Wrong CT ratio entered, wrong settings group | Compare relay settings with schedule; verify CT ratio |
| Loop reads wrong value in SCADA | Scaling mismatch, wiring polarity, wrong range | Check LRV/URV in transmitter, PLC and SCADA; inject known current |
Test record quality check
0 / 8- Every record shows
- Follow-up
08Test yourself
Ten questions with explanations. Scores are saved only in your browser and feed your learning progress dashboard.