Cables are the longest-lived and least visible assets in a distribution network. A cable that is correctly selected, carefully installed, properly jointed and tested will outlast most of the equipment it connects; a poorly made joint can fail within months.

What this department covers

  • MV and LV cable construction
  • Selection and sizing checks
  • Installation methods and derating
  • Pulling, bending and handling
  • MV joints and terminations
  • Screen bonding
  • Testing before and after energisation
6 checksrating, derating, ΔV, short circuit, earth fault, installation
U₀/U (Um)voltage designation matched to the system
S = √(I²t)/kadiabatic short-circuit sizing
Screencontinuity through every joint and termination

01Cable construction

An MV cable is an insulation system as much as a conductor. Around the stranded copper or aluminium conductor sit a semi-conductive conductor screen, the main insulation (commonly XLPE or EPR), a semi-conductive insulation screen, a metallic screen of copper wires or tape, and protective layers — bedding, armour where specified, and an oversheath. The semi-conductive layers keep the electric field radial and free of air voids at the insulation boundaries; the metallic screen carries capacitive charging current and earth-fault current and must be bonded and continuous.

Layers of a typical screened single-core XLPE MV cable
Figure 1.Layers of a typical screened single-core XLPE MV cable. Materials, armour type and water-blocking depend on the cable specification.

LV cables are simpler — insulated cores (PVC or XLPE), often laid up as multicore with or without armour (steel wire armour for multicore, aluminium wire armour or no armour for single-core AC to avoid induced heating in magnetic armour) and an oversheath. Fire-performance cables (low smoke zero halogen, fire-resistant) are specified by the project where life-safety or building requirements demand them.

Cable construction elements and why they matter
ElementFunctionReview point
Conductor (Cu / Al, class)Carries load currentMaterial and cross-section vs design; compatible lugs/connectors (Al needs suitable fittings)
Insulation (XLPE, EPR, PVC)Withstands voltage; sets maximum conductor temperatureVoltage designation; temperature limits used in rating calculations
Semi-conductive screensField control at conductor and insulation surfacesBonded vs strippable type — affects jointing kit choice
Metallic screenEarth-fault current path; field confinementCross-section adequate for earth-fault current and duration
ArmourMechanical protection; may form part of protective conductorMagnetic armour not used on single-core AC circuits
OversheathMoisture and mechanical protectionMaterial per environment (PE, PVC, LSZH); termite/UV requirements if specified

02Selection and sizing — the six checks

No cable is selected on current alone. A sound selection satisfies every one of these checks at the same time, and the result is the largest cross-section any of them requires.

  1. Voltage designation.The cable's rated voltage (U₀/U and Um) suits the system nominal and highest voltage and its earthing arrangement.
  2. Continuous current rating.Using manufacturer or standard rating data for the actual construction and installation method, corrected for ambient/ground temperature, soil thermal resistivity, depth, grouping and ducts.
  3. Voltage drop.Under maximum design current, and for motors also during starting, within the project's limits.
  4. Short-circuit thermal withstand.Conductor (and screen) withstand the prospective fault current for the protection clearing time.
  5. Earth-fault performance.On LV, the earth-fault loop impedance allows the protective device to disconnect within the required time; on MV, screen capacity is adequate.
  6. Installation and compatibility.Bending radius, pulling tension, termination space, gland sizes, lug compatibility and route constraints.
Buried installation conditions — depth, spacing, bedding and grouping — directly change the cable's current rating
Figure 2.Buried installation conditions — depth, spacing, bedding and grouping — directly change the cable's current rating.
Factors that reduce a buried cable's current rating
FactorEffectWhere it comes from
Higher ground/ambient temperatureLess temperature headroom → lower ratingSite data and project design basis
Higher soil thermal resistivityHeat cannot escape → lower ratingSoil survey; thermal backfill may be specified
Grouping / reduced spacingMutual heating between circuitsRoute design; rating factors for the arrangement
Installation in ductsAir gap adds thermal resistanceDuct sizing and fill; manufacturer duct ratings
Greater burial depthSlightly lower rating (and better mechanical protection)Approved trench detail
Solar radiation (above ground)Additional heat gainExposed routes, trays on rooftops

The adiabatic equation gives a quick check of conductor short-circuit withstand. It assumes all heat is retained in the conductor during the fault, which is reasonable for short durations.

S ≥ √(I² · t) / kS = cross-section (mm²); I = fault current (A rms); t = duration (s); k depends on conductor material and its initial and final temperatures. Typical published values include k ≈ 143 (Cu, XLPE) and 115 (Cu, PVC); confirm for the actual cable.

03Installation: handling, pulling and bending

Most installation defects are mechanical: insulation damaged by sharp bends, sheaths scuffed during pulling, water entering cut ends, or cables crushed in poorly prepared trenches. The manufacturer's limits for pulling tension, sidewall pressure and minimum bending radius govern; the radius is normally stated as a multiple of the cable's overall diameter and is larger during pulling than for the final set position.

  1. Inspect drums on receipt.Check drum and cable identification against the approved submittal, look for drum damage, confirm cap seals on both ends and record lengths.
  2. Prepare the route.Trench excavated to the approved depth and width, bottom levelled and free of stones, bedding laid; ducts proven clear with a mandrel; road crossings and service crossings protected.
  3. Plan the pull.Drum position, direction, rollers at bends and entries, pulling method (stocking or eye), dynamometer where tensions are significant, communication between ends.
  4. Pull and lay.Pull at steady speed within tension limits; keep bending radius above the minimum; maintain formation (trefoil/flat) and spacing per design; avoid crossings within the formation.
  5. Seal and protect.Re-seal cut ends immediately; install cover tiles, warning tape and backfill per detail; record route and depth for as-builts.
  6. Test before backfillingwhere the ITP requires (commonly an oversheath or insulation resistance test) to catch damage while it is still accessible.

Never leave MV cable ends unsealed. Moisture entering the conductor or screen can migrate along the cable and cause premature insulation failure long after energisation.

04MV joints and terminations

A joint must rebuild every functional layer of the cable across the connection: conductor continuity through a connector, insulation thickness, stress control at the screen cut, the semi-conductive outer layer, metallic screen continuity and the outer protection. Terminations do the same at the end of the cable, with stress control and — outdoors — additional creepage distance via sheds.

Functional layers of an MV straight joint
Figure 3.Functional layers of an MV straight joint.
MV cable termination
Figure 4.MV cable termination. The stress control at the screen cut-back is the critical design feature.
Joint/termination quality controls
StageCritical controlTypical defect if missed
Kit selectionKit matches cable type, voltage, conductor size and screen typeWrong stress control; poor fit; early failure
EnvironmentDry, clean, sheltered work area; tools clean; hands/gloves cleanContamination at insulation interface → tracking
Cut-back dimensionsExactly per kit instructions, measured and markedStress concentration; insufficient creepage
Screen removalSquare cut, no nicks into insulation, all semi-con removed where requiredPartial discharge at screen edge
Insulation surfaceSmooth, no scores, cleaned with approved solvent in the correct directionVoids/tracking paths
ConnectorCorrect lug/connector type and die; shear-bolts fully sheared; edges smoothedHot joints; field enhancement at sharp edges
Screen continuityScreen connector/mesh applied and securedLoss of earth-fault path; induced voltage hazards
RecordingJointer name/competency, kit batch, date, location, photos at hold pointsNo traceability when investigating failures

05Screen bonding and induced voltages

For single-core MV cables, current in the conductor induces voltage in the metallic screen. If screens are bonded to earth at both ends, circulating currents flow and add losses that reduce the cable rating; if bonded at one end only, a standing voltage appears at the open end and must be limited and protected. Long high-current circuits sometimes use cross-bonding. The bonding method is a design decision that affects rating, safety and earthing — it must be shown on the drawings and installed exactly as designed.

06Testing cables

Typical cable tests include insulation resistance, continuity and phasing, oversheath integrity (where specified), and for MV cables an after-installation withstand test — commonly a very-low-frequency (VLF) AC test or another method specified by the project or utility (DC withstand testing is generally discouraged for XLPE insulation by many references) — sometimes with partial-discharge or tan δ diagnostics. The test method, voltage, duration and acceptance criteria are those of the approved ITP, the cable/accessory manufacturer and the applicable standard; they are not universal.

Cable tests use hazardous voltages and long cables store significant charge. Apply the permit system, barrier the far end, and discharge and earth the cable after every test.

07Troubleshooting

Cable troubleshooting
SymptomLikely causesChecks
Low insulation resistance on one coreSheath/insulation damage, moisture at an end, contaminated terminationSectionalise; clean and re-test terminations; check end caps; locate fault if persistent
Joint failure soon after energisationWorkmanship (contamination, cut-back error), wrong kitFailure investigation with jointing records and photos; review competency and kit
Cable hot under loadOverload, grouping, poor thermal backfill, both-end bonding on high-current single-coreLoad logging; compare with rating basis; check bonding arrangement
Nuisance earth-fault tripsDamaged insulation, moisture, long cable capacitive leakageIR test; check earth-fault settings vs charging current
Voltage drop complaintsUndersized cable, longer route than designedCompare as-built length; recalculate with actual load

Cable installation & jointing inspection

0 / 13
  • Before laying
  • During laying
  • Jointing & termination
  • Close-out
Ticks are saved only in this browser. Adapt the list to the approved ITP and manufacturer instructions; it does not define acceptance criteria.

08Test yourself

Ten questions with explanations. Scores are saved only in your browser and feed your learning progress dashboard.