Electrical interview question bank.
60 questions asked in site engineer, QA/QC, testing & commissioning and protection interviews — with model answers written to show method and judgement, not memorised numbers.
01What do you check before laying an MV cable in a trench?
Confirm the trench against the approved detail (route, depth, width, bedding), that the cable on the drum matches the approved submittal (type, size, voltage designation, drum ID), that the bending radius and pulling plan are agreed, that ducts at crossings are proven clear, and that cut ends are sealed. Raise an inspection request before laying and again before backfilling, and complete any pre-backfill test the ITP requires. Read more →
02What is the difference between an MDB, SMDB and DB?
They are levels of the LV radial hierarchy. The main distribution board (MDB) is fed from the transformer and distributes to sub-main boards (SMDBs), MCCs and large loads. SMDBs feed distribution boards (DBs) in an area, and DBs feed final circuits through MCBs/RCBOs. Each outgoing device is sized for its cable and load and coordinated with the devices above and below it. Read more →
03How do you coordinate electrical work with civil and mechanical teams?
Use coordinated services drawings, agree sleeves, openings and trench routes before concrete is poured, confirm equipment sizes, weights and access routes early, and hold regular coordination meetings with clear action owners. When drawings conflict, raise an RFI to get a recorded design answer instead of resolving it informally on site. Read more →
04What information do you take from a single-line diagram before energising a board?
Source and voltage levels, the incoming device and its rating, outgoing devices and ratings, CT/VT data and protection functions, the earthing arrangement and neutral–earth link location, normally-open points and interlocks, and cable references. I compare this with the as-installed board, the settings schedule and the test records before energisation. Read more →
05How do you verify a cable route length for the cable schedule?
Measure along the actual route including vertical runs, bends and the termination allowance at each end, then compare with the drawing length. Record the measured length in the cable schedule; it is used for voltage drop, ordering and as-built records. Significant differences from the design length are reported because they can affect voltage drop and earth-fault loop impedance. Read more →
06A delivered transformer's nameplate impedance differs from the approved datasheet. What do you do?
Quarantine the unit for acceptance, raise a material inspection rejection or NCR, and inform the designer. Impedance affects LV fault level, voltage regulation and paralleling, so the designer must re-check switchgear breaking capacity, protection settings and voltage drop before any decision. The unit is only accepted with a documented engineering evaluation and client/consultant approval. Read more →
07Why are torque marks used on electrical connections?
After a bolted connection is tightened to the manufacturer's torque with a calibrated tool, a paint line across the nut and stud shows it has been torqued and makes any later movement visible during inspection. They support the inspection record but do not replace using the correct torque value.
08What is the purpose of a cable schedule?
It is the master list of every cable: ID, origin and destination, type, cores and size, voltage designation, length, route, gland and lug details and status (laid, terminated, tested). It drives procurement, installation tracking, testing and as-built documentation. Read more →
09What is an ITP and what are hold and witness points?
An Inspection and Test Plan lists each inspection and test, the reference document and acceptance criteria, the record produced and the involvement of each party. A Hold point means work stops until the inspection is released; a Witness point means the client/consultant must be notified and may attend; a Review point is a document review. Read more →
10What is the difference between QA and QC?
Quality assurance is the planned system that prevents defects — procedures, ITPs, approvals, training and audits. Quality control is the checking of actual work and materials against requirements — inspections, tests and records. QA defines how quality is achieved; QC verifies that it was. Read more →
11How do you review an electrical material submittal?
Check it against the latest specification and drawings: correct item and model, ratings, compliance with each specified clause (a clause-by-clause compliance statement), datasheets with the offered model highlighted, type-test and routine-test evidence that actually covers the offered design, approvals required by the project, and declared deviations. Missing evidence is recorded and requested instead of assumed. Read more →
12What makes a good NCR process?
Clear description of the non-conformance with evidence, containment of affected work, root-cause analysis, corrective action for this case, preventive action to stop recurrence, a defined disposition (rework, repair, replace or use-as-is with engineering acceptance) and verified closure with records. Read more →
13What do you check in a material inspection on delivery?
That the delivered item matches the approved submittal (manufacturer, model, ratings, quantity), is undamaged, has the required certificates and identification, and is stored and protected correctly. Any mismatch is rejected or quarantined pending evaluation.
14Is a type-test certificate enough to accept a switchboard?
Not by itself. A type test applies to a specific design. You must confirm the certificate covers the offered design, ratings and configuration, is from an acceptable laboratory where specified, and is supported by routine tests on the actual unit. For LV assemblies, design verification evidence under the applicable assembly standard and the project specification govern acceptance. Read more →
15What should every test record contain?
Equipment and circuit identification, test method, test voltage/current and duration, instrument make, model, serial number and calibration validity, ambient conditions where relevant, measured values, the acceptance criterion and its source, the result, and names, signatures and date — plus witness signatures at witness points. Read more →
16Why do we perform an insulation resistance test?
To check the condition of insulation between conductors and between conductors and earth, revealing damage, moisture or contamination before energisation. It is a DC test at a voltage chosen for the equipment rating; results are compared with manufacturer or specified criteria and earlier results, and the circuit is discharged afterwards. Read more →
17What is the polarisation index and why is it useful?
PI is the ratio of insulation resistance at 10 minutes to that at 1 minute. Clean, dry insulation shows increasing resistance as absorption current decays, giving a higher ratio; moist or contaminated insulation gives a ratio closer to 1. It is used mainly for rotating machines and windings and is interpreted with equipment-specific guidance. Read more →
18Which site tests are typically done on a distribution transformer?
Visual and mechanical inspection, insulation resistance, winding resistance, turns ratio at the taps, vector group check, oil tests where specified, and functional tests of temperature, pressure and Buchholz devices through to trip and alarm, plus protection injection of the upstream relay. Scope and criteria come from the approved ITP and manufacturer. Read more →
19What is the difference between primary and secondary injection?
Secondary injection applies current/voltage at the relay terminals to test the relay's pick-up, timing and logic. Primary injection drives current through the primary conductor and CT, proving the CT ratio, polarity and secondary wiring as well as the relay response. Read more →
20Why must a cable be discharged after an insulation test?
Long cables and windings behave as capacitors and store charge from the DC test voltage. Touching them before discharging through an approved device can give a dangerous shock. Discharge for at least as long as the procedure requires, then apply earths.
21What do you check immediately after energising a new LV board?
Voltages phase-to-phase and phase-to-neutral, phase rotation, correct indications and metering, no abnormal noise, smell or heat, and — before closing any parallel or ring connection — phasing. After a period on load, record currents and perform thermography of connections. Read more →
22What is a loop check in instrumentation?
Verifying each signal from the field device through wiring and I/O to the control system and HMI — for analogue signals at several points across the range (for example 4, 8, 12, 16 and 20 mA) — confirming tag, scaling, units and alarms. Read more →
23A new MV cable shows low insulation resistance on one core. What next?
Do not energise. Check and clean terminations, confirm end caps and that no equipment is connected, re-test, and if still low sectionalise at joints to locate the fault, then use fault-location methods. Record results, raise an NCR and repair or replace the defective section, followed by the full specified test. Read more →
24What does selectivity (discrimination) mean?
For any fault, only the protective device nearest the fault operates, so the rest of the system stays in service. It is achieved by grading time–current characteristics and verified with curves and manufacturer selectivity tables at the fault levels that occur. Read more →
25What do TMS and Is mean on an IDMT relay?
Is (pick-up) is the current above which the relay starts timing. TMS (time multiplier setting) scales the operating time of the chosen inverse curve. Higher TMS means slower operation at all currents; the curve shape is set by the characteristic (standard, very or extremely inverse). Read more →
26Why must a CT secondary never be open-circuited on load?
Without the opposing secondary ampere-turns, the primary current drives the core into saturation and very high peak voltages appear across the open secondary — dangerous to people and to insulation. Short the CT at the test terminal block before disconnecting meters or relays. Read more →
27What is the difference between a load-break switch and a circuit breaker?
A load-break switch can make and break normal load current but cannot interrupt fault current. A circuit breaker can interrupt fault current up to its rated breaking capacity, usually under the control of a protection relay or trip unit. Read more →
28What is Icu and Ics on an LV breaker?
Icu is the rated ultimate short-circuit breaking capacity; Ics is the rated service short-circuit breaking capacity, after which the breaker remains fit for further service. Both must be considered against the prospective fault current at the installation point. Read more →
29Why is second-harmonic restraint used in transformer differential protection?
Magnetising inrush on energisation appears as a large current on one side only, which a differential relay would see as an internal fault. Inrush is rich in second harmonic, so the relay blocks or restrains operation when the second-harmonic content is high. Read more →
30What does a fault passage indicator do on an RMU?
It shows whether fault current has passed through that way, helping operators locate the faulted cable section on a ring so it can be isolated and supply restored to healthy sections. Read more →
31What are interlocks on switchgear for?
To prevent unsafe operating sequences — for example closing an earth switch on a live circuit or opening a cable compartment that is not earthed. They are never bypassed; the operating sequence follows the manufacturer's manual and safety rules. Read more →
32How do you calculate three-phase load current?
I = P / (√3 × V_LL × PF), with P in watts. For example 100 kW at 400 V and PF 0.9 gives about 160 A. For apparent power, I = S / (√3 × V_LL). Read more →
33What checks decide a cable size?
Voltage designation, continuous current rating after correction factors for the actual installation, voltage drop, short-circuit thermal withstand, earth-fault loop impedance / disconnection time, and installation constraints. The governing size is the largest required by any check. Read more →
34How does transformer impedance affect the LV system?
Higher impedance reduces prospective fault current (easier switchgear duty) but increases voltage regulation under load and during motor starting. With an infinite source, I_sc ≈ I_rated × 100 / Z%. Read more →
35Why is power factor correction applied and what is a detuned bank?
Correcting PF reduces current, losses and voltage drop and frees capacity; required kvar = P(tan φ1 − tan φ2). A detuned bank adds series reactors so the capacitor circuit is tuned below the dominant harmonics, avoiding resonance where non-linear loads are present. Read more →
36What are demand factor and diversity?
Demand factor is maximum demand divided by connected load for a group. Diversity recognises that the maximum demands of different groups do not occur at the same time. Both must be justified by the design basis and applied at the correct level to avoid double counting. Read more →
37What is the meaning of Dyn11 and why is it common for distribution?
HV delta, LV star with neutral brought out; the clock number 11 means 330° lag, i.e. the LV leads the HV by 30°. The delta circulates triplen harmonics and the star neutral supports single-phase loads and LV system earthing. Read more →
38Why do street lighting circuits use phase rotation?
Connecting columns L1, L2, L3 in sequence balances the load across phases and spreads each phase's luminaires along the route, reducing neutral current and voltage unbalance. Read more →
39What are the steps of safe isolation?
Plan under the safety rules, switch off, isolate at all supply points, lock and tag, prove dead with an approved tester (proving the tester before and after), apply earths where required, issue the permit, then cancel and restore in the correct order after work. Read more →
40Is a voltage presence indicator proof that a circuit is dead?
No. VPIS and mimic positions are indications only. Dead must be proved with an approved test performed as the safety rules require.
41What is the difference between earthing and bonding?
Earthing connects parts of the installation to earth so fault current has a path and protection operates. Protective equipotential bonding connects conductive parts together so they stay at similar potential during a fault, limiting touch voltage. Read more →
42What are touch and step voltage?
Touch voltage is between earthed metalwork a person touches and the ground at their feet; step voltage is between two feet a stride apart on the ground surface during an earth fault. Substation earthing is designed to keep both within tolerable limits. Read more →
43Why should you never defeat an interlock even if the switch seems stuck?
A stuck operation usually means a condition is not met — for example the earth switch is closed or the main switch is in an intermediate position. Forcing or bypassing it can cause an operation onto a live or earthed circuit, arc flash or equipment damage. Stop, check the manual and escalate. Read more →
44What is a permit-to-work?
A formal written authorisation, issued by an authorised person, defining the equipment, safety precautions taken (isolation, earthing), limits of work and the person in charge. Work only proceeds within its limits and it is formally cleared and cancelled before re-energisation.
45The client wants to energise tomorrow but two test records are missing. What do you do?
Explain that energisation is a hold point that depends on complete, reviewed evidence. Prioritise completing the missing tests, review the results, and propose a revised time. Energising without evidence exposes people and equipment to risk and the project to liability.
46A subcontractor installed cables to a superseded drawing. How do you handle it?
Stop further work on the affected area, raise an NCR, assess the impact with the designer (routing, length, voltage drop, sizes), agree rework or acceptance, and fix the root cause — document control and withdrawal of superseded drawings from site. Read more →
47During commissioning a feeder breaker trips immediately on closing. What is your approach?
Do not keep re-closing. Check event records and relay flags, confirm the downstream circuit state (earth switches, equipment connected), test insulation of the outgoing circuit, verify relay settings and inrush allowance, and inspect trip circuit wiring. Re-close only after the cause is found and under the authorised switching procedure. Read more →
48Tell us about a time you found a mistake in a drawing.
Use a structured answer: the situation, what you noticed (for example cable size inconsistent with the load schedule), how you verified it, how you raised it (RFI with evidence and a proposed solution), and the result. Show that you raised it formally and early, not that you fixed it informally.
49How do you prepare for a consultant's inspection?
Complete a self-inspection first, close obvious defects, have approved drawings, submittals and test records available, ensure the area is safe and accessible, and raise the inspection request with the required notice period. Walk the inspector through the work with evidence ready.
50How do you measure the resistance of an earth electrode?
Commonly with the fall-of-potential (three-pole) method: disconnect the electrode from the system where safe and permitted, place the current and potential spikes in a straight line at distances suited to the electrode size, and take readings at several potential-spike positions to confirm a plateau. Record soil condition and weather, because results vary seasonally. Read more →
51What is a VLF test and when is it used?
A very-low-frequency (typically around 0.1 Hz) AC withstand test used on MV cables after installation or repair, where a power-frequency test set would be too large. Test voltage, duration and any diagnostic measurements (such as tan δ or partial discharge) come from the cable standard, manufacturer and project specification. Read more →
52What is a phase rotation test and why is it needed?
It confirms the sequence L1-L2-L3 at a point in the system. Wrong rotation reverses three-phase motors — dangerous for pumps, lifts and fans — and must be correct before connecting rotating loads or paralleling sources. Read more →
53How do you check a street lighting column installation?
Foundation and anchor bolts per detail, column verticality and door orientation, cable entry and looping, cut-out and fuse rating, earth connection to the column and cut-out, luminaire type and wattage against the approved submittal, phase allocation per the drawing, IR and continuity tests and a functional check of the photocell or control system. Read more →
54What do you check during pump station electrical installation?
MCC/panel position and access, motor cable sizes and glands, VFD or soft-starter settings and cable screening, level instruments and float switches, local isolators, earthing and bonding of pumps and pipework, interlocks and duty/standby logic, rotation check before coupling, and SCADA signals. Read more →
55Why are screened (EMC) cables used between a VFD and a motor?
The VFD output has fast-switching voltage edges that radiate interference and cause capacitive currents. A symmetrical screened cable with 360° screen termination at both ends returns those currents in a controlled path, reducing EMC problems and bearing currents. The drive manufacturer's cable length and installation rules apply. Read more →
56What is the difference between TN-S, TN-C-S and TT earthing systems?
In TN systems the source neutral is earthed and exposed parts connect to it: TN-S keeps separate neutral and protective conductors throughout, TN-C-S combines them (PEN) in part of the system. In TT the installation's exposed parts are connected to a local earth electrode independent of the source earth, so earth-fault currents are low and RCDs are usually needed for disconnection. Read more →
57What is the purpose of a trip circuit supervision relay?
It continuously monitors the breaker trip coil circuit — wiring, coil and auxiliary contacts — in both breaker positions where configured, and alarms if the circuit is broken, so a protection trip will not silently fail. Read more →
58What is a FAT and how is it different from a SAT?
A Factory Acceptance Test verifies equipment — for example a control panel or PLC system — at the manufacturer's works against the approved design before shipment. A Site Acceptance Test verifies the installed system on site with real field devices and interfaces. Both follow approved procedures with recorded results. Read more →
59What is the purpose of as-built drawings?
They record what was actually installed — routes, sizes, lengths, positions and changes from the design — so the owner can operate, maintain and extend the system safely. They are verified against site records and approved before handover. Read more →
60Your test equipment's calibration expired yesterday. Can you continue testing?
No — results from an instrument outside calibration are not valid evidence under a normal quality system. Stop using it, use a calibrated instrument, and assess whether earlier results are affected if the instrument is later found out of tolerance.
How to use these answers. Interviewers look for structured thinking: what you check, why, which document governs it and who you involve. Put answers in your own words and support them with examples from your own projects. Values and acceptance criteria always come from the approved specification, the manufacturer and the applicable standard — not from a general answer.