Seniors & managers

Lessons learned.

12 typical project problems — what happened, the real root cause and how to stop it happening on your next project.

01

Transformer energised with tap at the wrong position

Transformers
What happened

LV voltage was about 5 % high after energisation; several sensitive loads alarmed.

Root cause

Tap position not checked against the design setting; commissioning checklist had no tap item.

How to prevent it

Add tap position (and the expected LV voltage) to the pre-energisation checklist; record it with a photo.

02

Cable failed a month after energisation

Cables
What happened

A new MV cable failed at a joint in the first month.

Root cause

Joint made in the open during dusty, humid conditions; the kit's cleanliness instructions were not followed; no shelter.

How to prevent it

Joint only in a clean, covered enclosure; jointer competence record; check kit expiry and instructions at the ITP hold point.

03

Pumps ran backwards at handover

Pump stations
What happened

Two pumps ran in reverse during the first test; one impeller was damaged.

Root cause

Phase rotation not checked after the supply cable was re-terminated; motors were bump-tested coupled.

How to prevent it

Check phase rotation at the MCC and bump-test uncoupled after any re-termination.

04

Breaker could not clear a fault

Protection
What happened

During a short-circuit study review, a final DB's MCB was found to have a breaking capacity below the prospective fault current.

Root cause

DB moved closer to the transformer during design changes; fault level not recalculated.

How to prevent it

Recalculate fault levels after any layout change; include Icu checks in the design change checklist.

05

Incomer tripped on energising a large transformer

Protection
What happened

Upstream breaker tripped every time a transformer was energised.

Root cause

Instantaneous setting below the transformer's magnetising inrush current.

How to prevent it

Check inrush against instantaneous settings during coordination studies; review settings before energisation.

06

RCDs tripping randomly on a lighting circuit

LV distribution
What happened

Many nuisance trips on an LED lighting circuit.

Root cause

Too many LED drivers on one RCD — cumulative earth leakage and switching inrush.

How to prevent it

Limit drivers per RCD per manufacturer data; split circuits; use suitable RCD types.

07

Wrong cable size installed for a whole floor

Site
What happened

Final circuits installed in 2.5 mm² where the revision required 4 mm².

Root cause

Superseded drawing left in the site office; the crew used it.

How to prevent it

Drawing register checks, stamp and remove superseded prints, issue revision notices at toolbox talks.

08

Earth pit readings much higher in summer

Earthing
What happened

Handover earth resistance passed; summer readings were more than double.

Root cause

Measured during wet season; dry sandy soil; electrode too short.

How to prevent it

Design for dry-season resistivity; deeper electrodes or enhancement as designed; record conditions with readings.

09

VFD tripping and bearing damage

Pump stations
What happened

Motor bearings failed early; VFD gave repeated earth-fault trips.

Root cause

Unscreened motor cable, screens not terminated 360°, long cable run beyond drive guidance.

How to prevent it

Use the drive manufacturer's cable and gland requirements; output filters for long runs; check bearing-current mitigation.

10

Test results that didn't add up

Testing
What happened

Insulation readings were identical on every circuit and floor.

Root cause

Results copied rather than measured; test instrument calibration had expired.

How to prevent it

Witness sample tests; check instrument serial numbers and calibration on every sheet; random re-tests.

11

Flooded cable trench at a substation

Civil interface
What happened

Rainwater flowed through ducts into the RMU base and caused tracking.

Root cause

Duct ends not sealed after cable installation; no fall away from the substation.

How to prevent it

Seal ducts immediately; inspect duct sealing as an ITP item; coordinate drainage with civil.

12

Neutral overheating in an office DB

Power quality
What happened

The neutral conductor and terminal were discoloured though phases were within rating.

Root cause

Many single-phase non-linear loads; third-harmonic currents added in the neutral.

How to prevent it

Measure with true-RMS meters; size neutrals for harmonic loading; balance phases; consider filtering.