Distribution engineering is where network theory meets the plot of land, the substation room and the switchboard schedule. This department follows supply from the utility MV ring through the secondary substation to LV boards and final circuits.
What this department covers
- Open-ring MV networks and normally-open points
- Secondary (MV/LV) substation arrangements
- LV switchboards, SMDBs and DBs
- Load schedules and maximum demand
- Selectivity and discrimination
- Power factor correction
- Voltage drop budgeting
01MV networks: rings, feeders and normally-open points
Urban MV distribution is usually built as rings of cable that start and end at primary substations, with ring main units (RMUs) at each secondary substation along the route. The ring is normally operated open at one point so that each half is a simple radial feeder with straightforward protection. When a cable section fails, the faulted section is identified, isolated by opening the RMU switches either side, and supply is restored by closing the normally-open point (NOP) so the remaining substations are back-fed from the other end.
Design decisions at this level are usually made or approved by the distribution utility: ring capacity, number of substations per ring, cable type and size, NOP location, RMU type and the protection at the primary substation. A developer's project normally connects to this network according to the utility's connection requirements and approved material lists.
Switching on utility networks is carried out only by authorised persons under the network operator's switching programme and safety rules. Contractor commissioning teams must not operate network equipment unless specifically authorised.
02The secondary (MV/LV) substation
A secondary substation converts MV to LV for a group of consumers or a single large site. Its core components are an RMU (or MV switchgear), one or more distribution transformers, an LV distribution board and the interconnecting cables, plus earthing, ventilation and access provisions.
| Form | Description | Strengths | Points to check |
|---|---|---|---|
| Compact / package substation | Factory-assembled enclosure containing RMU, transformer and LV board | Fast installation, type-tested assembly | Ventilation/derating, access, maintenance clearances, internal arc classification where specified |
| Indoor substation room | Equipment installed in a building room | Protection from environment, flexible layout | Fire separation, oil containment, ventilation, cable trenches, door sizes |
| Pole-mounted / overhead | Small transformer on a pole with fuses | Low cost for rural/overhead networks | Clearances, lightning protection, earthing |
| Consumer substation | Dedicated substation for one large customer | Customer-specific configuration | Metering boundary, ownership limits, protection interfaces |
Ownership and the point of supply must be unambiguous: which party owns and operates the RMU, the transformer, the LV board and the metering — and where the responsibility for earthing, protection settings and maintenance changes.
03LV distribution hierarchy
On the LV side, distribution is normally radial: the main distribution board (MDB) feeds sub-main boards (SMDBs), motor control centres (MCCs) and distribution boards (DBs), which in turn feed final circuits. Each outgoing way is protected by a device sized to the cable and load it serves, and the devices are coordinated so that the one closest to a fault operates first.
| Level | Device (typical) | Key ratings to check | Common review issues |
|---|---|---|---|
| Transformer LV incomer | ACB or large MCCB with electronic trip | Rated current vs transformer rating, Icu/Ics and Icw vs fault level, earth-fault function | Settings left at factory defaults; neutral/earth link arrangement unclear |
| MDB outgoing ways | MCCB / ACB | Ir setting vs cable rating; breaking capacity at MDB fault level | Spare ways not shown; cable ratings not matched to settings |
| SMDB / MCC | MCCB, motor circuit breakers, contactors | Selectivity with MDB; motor starting coordination | Selectivity assumed but never checked |
| DB / final circuits | MCB, RCBO, RCD | Curve type, breaking capacity, earth-fault disconnection | RCD type unsuitable for loads with DC components |
04Load schedules and maximum demand
The load schedule is the numerical backbone of distribution design. It should list every circuit with its description, rating, phase allocation, power factor, demand factor and resulting design current, and it should total up through every level of the hierarchy so that cables, devices and transformers can be justified.
- List loads with real data.Use equipment data or reasoned allowances; flag assumptions.
- Allocate phases.Balance single-phase loads across L1, L2 and L3 and record the resulting phase currents.
- Apply demand and diversity.Use a documented basis — project specification, utility guidance or agreed engineering judgement — and apply it at the correct level.
- Compute design currents.Convert kW to current using voltage and power factor at each board.
- Select devices and cables.Device rating ≥ design current; cable capacity (after derating) ≥ device setting; voltage drop and fault withstand checked.
- Carry totals upstream.Demand at each board feeds the next level up, ending with the transformer and utility application.
05Selectivity and protection coordination on LV
Selectivity (discrimination) means that for any overcurrent the device immediately upstream of the fault operates while all other devices remain closed. Overload selectivity is usually achieved by setting ratios; short-circuit selectivity requires comparing time–current characteristics at the prospective fault current and is best verified with manufacturer selectivity tables for the specific device combination. Cascading (back-up protection) allows a downstream device with lower breaking capacity to be used where the upstream device limits the let-through energy — but only for combinations tested and published by the manufacturer, and usually at the cost of selectivity.
Selectivity is never assumed from ratings alone. Two MCCBs with ratings of 400 A and 100 A may or may not be selective at 20 kA — only the manufacturer data for that pair and those settings can answer it.
06Voltage drop budgeting
Voltage at the load terminals must stay within the limits required by the project, the utility and the equipment. The total drop is the sum of the drops in each series element — transformer (under load), main cable, sub-main and final circuit — so designers allocate a budget to each level rather than checking only the final circuit. The project specification states the permissible limits; the voltage-drop guide and the homepage Cable Circuit Analysis workbench explain the calculation.
07Troubleshooting distribution problems
| Symptom | Likely causes | Checks |
|---|---|---|
| One phase significantly more loaded | Poor phase allocation, single-phase load growth | Clamp-meter survey per phase; re-balance circuits in the DB schedule |
| MDB incomer trips on earth fault | Downstream insulation fault, incorrect N–E links, neutral currents through earth paths | Check N–E link location(s); IR test outgoing circuits; review earth-fault settings |
| Transformer running hot | Overload, harmonics, ventilation, tap mismatch | Load profile logging; harmonic measurement; check ventilation path and ambient |
| Capacitor bank steps cycling rapidly | Controller settings, CT location/polarity, fluctuating load | Verify CT location and polarity; adjust C/k and switching delay |
| Voltage dips on motor starting | Large DOL starts on weak supply | Measure dip; consider reduced-voltage starting or drives |
Secondary substation & LV board pre-energisation review
0 / 10- Documents
- Installation
- Testing
08Test yourself
Ten questions with explanations. Scores are saved only in your browser and feed your learning progress dashboard.