Challenge
Spot the mistake.
5 real-world style documents and drawings with 31 hidden errors — a test record, a cable schedule, a single-line diagram, a distribution board and an NCR. Find them all.
Insulation test record
This test record was submitted for approval. Find what makes it unacceptable. Click on each mistake.
| Project | Compound B — Building 2 | Date of test | 2026-11-12 |
|---|---|---|---|
| Circuit ID | C-B2-021 | Cable | 4c 25 mm² Cu XLPE/SWA, SMDB-B2 → DB-B2-03 (schedule ID C-B2-012) |
| Instrument | Insulation tester, S/N 4471-22 | Calibration due | 2026-10-30 |
| Test voltage | 1000 V DC, 1 min | Acceptance | ≥ 100 MΩ (Spec. 26 05 19, ITP item 5) |
| L1-L2 | L2-L3 | L3-L1 | L1-E | L2-E | L3-E | N-E | Result |
|---|---|---|---|---|---|---|---|
| >2000 MΩ | >2000 MΩ | >2000 MΩ | 1450 MΩ | 48 MΩ | 1600 MΩ | — | PASS |
| Tested by | A. Rahman — 2026-11-12 | Witnessed by (consultant) |
|---|
Cable schedule extract
A cable schedule extract for Level 2. Several lines contain errors that should be caught before cables are pulled. Click on each mistake.
| Cable ID | From | To | Type | Size | Protective device | Length (m) | ΔV % | Limit | Status |
|---|---|---|---|---|---|---|---|---|---|
| C-L2-01 | MDB-1 | SMDB-L2 | 4c Cu XLPE/SWA | 4c 185 mm² | MCCB 400 A | 62 | 1.4 | 4 % | Tested |
| C-L2-02 | SMDB-L2 | DB-L2-A | 4c Cu XLPE/SWA | 4c 16 mm² | MCCB 200 A | 45 | 1.9 | 4 % | Laid |
| C-L2-03 | SMDB-L2 | SMDB-L2 | 4c Cu XLPE/SWA | 4c 35 mm² | MCCB 125 A | 38 | 1.2 | 4 % | Laid |
| C-L2-02 | SMDB-L2 | DB-L2-C | 4c Cu XLPE/SWA | 4c 25 mm² | MCCB 100 A | 70 | 2.6 | 4 % | Pulled |
| C-L2-05 | SMDB-L2 | DB-L2-D | 4c Cu XLPE/SWA | 4c 10 mm² | MCCB 40 A | 3.1 | 4 % | Laid | |
| C-L2-06 | SMDB-L2 | Pump P-2 | 4c Cu XLPE/SWA | 4c 6 mm² | MPCB 16 A | 140 | 5.8 | 4 % | Tested ✓ OK |
Single-line diagram
A preliminary SLD for review. Find the design mistakes. Click on each mistake.
Distribution board inspection
You are inspecting a newly installed DB with the door removed. Find the defects. Click on each mistake.
NCR form
This NCR was submitted for closure. What's wrong with it? Click on each mistake.
| Date raised | 2026-11-03 | Raised by | QA/QC Electrical |
|---|---|---|---|
| Description | Cables not installed correctly. To be corrected. | ||
| Requirement | — | ||
| Containment | Work stopped on tray T-4, Level 3; affected cables tagged "on hold". | ||
| Root cause | Worker error. | ||
| Disposition | Rework: re-route cables C-12 to C-18 per drawing E-201 Rev D. | ||
| Preventive action | None required. | ||
| Closure verified by | Subcontractor foreman | Closure date | 2026-11-01 |
All documents are invented for training. Names, numbers and references are fictitious.