Challenge

Spot the mistake.

5 real-world style documents and drawings with 31 hidden errors — a test record, a cable schedule, a single-line diagram, a distribution board and an NCR. Find them all.

Testing & QA/QC

Insulation test record

This test record was submitted for approval. Find what makes it unacceptable. Click on each mistake.

INSULATION RESISTANCE TEST RECORDForm QC-E-07
ProjectCompound B — Building 2Date of test2026-11-12
Circuit IDC-B2-021Cable4c 25 mm² Cu XLPE/SWA, SMDB-B2 → DB-B2-03 (schedule ID C-B2-012)
InstrumentInsulation tester, S/N 4471-22Calibration due2026-10-30
Test voltage1000 V DC, 1 minAcceptance≥ 100 MΩ (Spec. 26 05 19, ITP item 5)
L1-L2L2-L3L3-L1L1-EL2-EL3-EN-EResult
>2000 MΩ>2000 MΩ>2000 MΩ1450 MΩ48 MΩ1600 MΩ—PASS
Tested byA. Rahman — 2026-11-12Witnessed by (consultant)
    Design & site

    Cable schedule extract

    A cable schedule extract for Level 2. Several lines contain errors that should be caught before cables are pulled. Click on each mistake.

    CABLE SCHEDULE — LEVEL 2 (extract)CS-02 Rev C
    Cable IDFromToTypeSizeProtective deviceLength (m)ΔV %LimitStatus
    C-L2-01MDB-1SMDB-L24c Cu XLPE/SWA4c 185 mm²MCCB 400 A621.44 %Tested
    C-L2-02SMDB-L2DB-L2-A4c Cu XLPE/SWA4c 16 mm²MCCB 200 A451.94 %Laid
    C-L2-03SMDB-L2SMDB-L24c Cu XLPE/SWA4c 35 mm²MCCB 125 A381.24 %Laid
    C-L2-02SMDB-L2DB-L2-C4c Cu XLPE/SWA4c 25 mm²MCCB 100 A702.64 %Pulled
    C-L2-05SMDB-L2DB-L2-D4c Cu XLPE/SWA4c 10 mm²MCCB 40 A3.14 %Laid
    C-L2-06SMDB-L2Pump P-24c Cu XLPE/SWA4c 6 mm²MPCB 16 A1405.84 %Tested ✓ OK
      Design

      Single-line diagram

      A preliminary SLD for review. Find the design mistakes. Click on each mistake.

      11 kV, from RMU TX-1 1000 kVA11/0.4 kV Dyd0 Z 6 % N ACB 1600 AIcu 50 kA MDB 400 V — prospective 23 kA MCCB 250 AIcu 10 kA 4c 150 mm² SMDB-1 MCCB 160 AIcu 36 kA 4c 35 mm² SMDB-2incomer MCCB 250 A MCCB 63 AIcu 36 kA 4c 16 mm² M Pump 45 kWFLC ≈ 82 A
        Site inspection

        Distribution board inspection

        You are inspecting a newly installed DB with the door removed. Find the defects. Click on each mistake.

        DB-L2-ADoor removed for inspection busbar Q1Q2Q3Q4Q5Q6Q7Q8 — earth bar gland plate Circuit chart: missing
          QA/QC

          NCR form

          This NCR was submitted for closure. What's wrong with it? Click on each mistake.

          NON-CONFORMANCE REPORTNCR-E-0042
          Date raised2026-11-03Raised byQA/QC Electrical
          DescriptionCables not installed correctly. To be corrected.
          Requirement—
          ContainmentWork stopped on tray T-4, Level 3; affected cables tagged "on hold".
          Root causeWorker error.
          DispositionRework: re-route cables C-12 to C-18 per drawing E-201 Rev D.
          Preventive actionNone required.
          Closure verified bySubcontractor foremanClosure date2026-11-01

            All documents are invented for training. Names, numbers and references are fictitious.