Interns & QA/QC

Site documents, explained.

How to read and fill in the five documents you'll use most — ITP, NCR, RFI, method statement and test sheet — field by field, with examples and common mistakes.

Inspection and Test Plan (ITP)

Purpose: defines every inspection and test for a type of work, the acceptance criteria, the record produced and who must be involved. It is agreed before work starts.

ITP — field by field
FieldWhat to writeCommon mistake
ActivityOne inspectable step, e.g. "Cable laying in trench"Combining several activities in one line
ReferenceDrawing, specification clause, manufacturer document"As per spec" without a clause
Acceptance criteriaMeasurable criterion from the referenceInventing a value
Verifying documentThe record: checklist, test sheet, photoNot linking a record
Contractor / Consultant / ClientH (hold), W (witness), R (review), S (surveillance)Hold points nobody can attend
Example ITP lines — LV cable installation (illustrative)
#ActivityReferenceAcceptanceRecordContr.Cons.
1Material receiptApproved submittalMatches approved type, size, drum IDMaterial inspection reportHW
2Trench / tray before layingRoute drawing, trench detailRoute, depth, bedding as detailInspection checklistHW
3Cable layingMethod statementBending radius, no damage, tagsChecklist + photosHR
4Pre-backfillTrench detailCover, tape, spacingChecklistHH
5Insulation resistanceSpecification / ITP criteria≥ specified valueTest sheetHW

Non-Conformance Report (NCR)

Purpose: records work or material that does not meet requirements, and drives a controlled fix.

NCR — field by field
FieldWhat to write
DescriptionWhat was found, where, against which requirement — with photos
ContainmentImmediate action to stop it spreading (stop work, quarantine)
Root causeWhy it happened — use "5 whys", not "worker error"
DispositionRework / repair / replace / use-as-is (with engineering approval)
Corrective actionFix for this case
Preventive actionChange to stop it happening again
Verification & closureWho checked it, evidence, date

Example of a weak NCR: "Cables wrongly installed. Will correct." — no location, no requirement, no root cause, no prevention. A strong NCR: "Cables C-12 to C-18 in tray T-4 installed to drawing E-201 Rev B; current is Rev D (route changed). Root cause: superseded drawing not withdrawn from site office. Preventive: drawing register check at toolbox talk; superseded prints stamped and removed."

Request for Information (RFI)

Purpose: asks the designer a formal question when documents are unclear or conflict, and records the answer.

Good RFI checklist
ElementExample
Clear subject"Conflict — DB-3F cable size between SLD and schedule"
ReferencesSLD E-101 Rev C shows 4c 35 mm²; cable schedule CS-02 Rev B shows 4c 25 mm²
Question"Please confirm the required size for DB-3F feeder."
Proposed solution"We propose 35 mm² as per SLD (load 95 A, MCCB 125 A)."
Impact"Cable pulling for level 3 starts on the 20th."
AttachmentsMarked-up extracts of both documents

Method statement

Purpose: explains how a task will be done safely and to specification. It is reviewed before work starts and briefed to the crew.

Method statement — typical sections
SectionContent
ScopeExactly what work is covered (and what is not)
ReferencesDrawings, specification, ITP, manufacturer instructions
ResourcesPeople and competencies, plant, tools, calibrated instruments
SequenceStep-by-step work sequence, including inspection points
Hazards & controlsFrom the risk assessment: isolation, lifting, excavation, heat, working at height
Quality checksWhat is checked at each step; link to ITP
Environment & housekeepingWaste, cable off-cuts, drum return
EmergencyContacts, first aid, rescue arrangements

Insulation resistance test sheet

What a complete test sheet contains
ItemExample
Project, area, dateBuilding B, Level 2, 2026-11-17
Circuit / cable IDC-B2-014, SMDB-B2 → DB-B2-03, 4c 25 mm² Cu XLPE
InstrumentMake, model, serial no., calibration due date (after test date!)
Test voltage & durationAs specified for the cable/system voltage
ResultsL1-L2, L2-L3, L3-L1, L-N, each L-E, N-E — with units
Acceptance criterionValue and its source (specification / ITP)
ResultPass / Fail for each
Ambient conditionsTemperature, humidity where relevant
SignaturesTested by, witnessed by, dates

Before you sign any test sheet

0 / 5
Ticks are saved only in this browser. Adapt the list to the approved ITP and manufacturer instructions; it does not define acceptance criteria.
You are offline — showing saved pages