Interns & QA/QC
Site documents, explained.
How to read and fill in the five documents you'll use most — ITP, NCR, RFI, method statement and test sheet — field by field, with examples and common mistakes.
Inspection and Test Plan (ITP)
Purpose: defines every inspection and test for a type of work, the acceptance criteria, the record produced and who must be involved. It is agreed before work starts.
| Field | What to write | Common mistake |
|---|---|---|
| Activity | One inspectable step, e.g. "Cable laying in trench" | Combining several activities in one line |
| Reference | Drawing, specification clause, manufacturer document | "As per spec" without a clause |
| Acceptance criteria | Measurable criterion from the reference | Inventing a value |
| Verifying document | The record: checklist, test sheet, photo | Not linking a record |
| Contractor / Consultant / Client | H (hold), W (witness), R (review), S (surveillance) | Hold points nobody can attend |
| # | Activity | Reference | Acceptance | Record | Contr. | Cons. |
|---|---|---|---|---|---|---|
| 1 | Material receipt | Approved submittal | Matches approved type, size, drum ID | Material inspection report | H | W |
| 2 | Trench / tray before laying | Route drawing, trench detail | Route, depth, bedding as detail | Inspection checklist | H | W |
| 3 | Cable laying | Method statement | Bending radius, no damage, tags | Checklist + photos | H | R |
| 4 | Pre-backfill | Trench detail | Cover, tape, spacing | Checklist | H | H |
| 5 | Insulation resistance | Specification / ITP criteria | ≥ specified value | Test sheet | H | W |
Non-Conformance Report (NCR)
Purpose: records work or material that does not meet requirements, and drives a controlled fix.
| Field | What to write |
|---|---|
| Description | What was found, where, against which requirement — with photos |
| Containment | Immediate action to stop it spreading (stop work, quarantine) |
| Root cause | Why it happened — use "5 whys", not "worker error" |
| Disposition | Rework / repair / replace / use-as-is (with engineering approval) |
| Corrective action | Fix for this case |
| Preventive action | Change to stop it happening again |
| Verification & closure | Who checked it, evidence, date |
Example of a weak NCR: "Cables wrongly installed. Will correct." — no location, no requirement, no root cause, no prevention. A strong NCR: "Cables C-12 to C-18 in tray T-4 installed to drawing E-201 Rev B; current is Rev D (route changed). Root cause: superseded drawing not withdrawn from site office. Preventive: drawing register check at toolbox talk; superseded prints stamped and removed."
Request for Information (RFI)
Purpose: asks the designer a formal question when documents are unclear or conflict, and records the answer.
| Element | Example |
|---|---|
| Clear subject | "Conflict — DB-3F cable size between SLD and schedule" |
| References | SLD E-101 Rev C shows 4c 35 mm²; cable schedule CS-02 Rev B shows 4c 25 mm² |
| Question | "Please confirm the required size for DB-3F feeder." |
| Proposed solution | "We propose 35 mm² as per SLD (load 95 A, MCCB 125 A)." |
| Impact | "Cable pulling for level 3 starts on the 20th." |
| Attachments | Marked-up extracts of both documents |
Method statement
Purpose: explains how a task will be done safely and to specification. It is reviewed before work starts and briefed to the crew.
| Section | Content |
|---|---|
| Scope | Exactly what work is covered (and what is not) |
| References | Drawings, specification, ITP, manufacturer instructions |
| Resources | People and competencies, plant, tools, calibrated instruments |
| Sequence | Step-by-step work sequence, including inspection points |
| Hazards & controls | From the risk assessment: isolation, lifting, excavation, heat, working at height |
| Quality checks | What is checked at each step; link to ITP |
| Environment & housekeeping | Waste, cable off-cuts, drum return |
| Emergency | Contacts, first aid, rescue arrangements |
Insulation resistance test sheet
| Item | Example |
|---|---|
| Project, area, date | Building B, Level 2, 2026-11-17 |
| Circuit / cable ID | C-B2-014, SMDB-B2 → DB-B2-03, 4c 25 mm² Cu XLPE |
| Instrument | Make, model, serial no., calibration due date (after test date!) |
| Test voltage & duration | As specified for the cable/system voltage |
| Results | L1-L2, L2-L3, L3-L1, L-N, each L-E, N-E — with units |
| Acceptance criterion | Value and its source (specification / ITP) |
| Result | Pass / Fail for each |
| Ambient conditions | Temperature, humidity where relevant |
| Signatures | Tested by, witnessed by, dates |