This guide provides a structured engineering review approach. Use it with approved project documents, equipment manufacturer instructions and the applicable standards and authority requirements.
011. Earthing versus bonding
Earthing connects designated parts of an electrical installation to the earthing system. Bonding connects exposed-conductive-parts and relevant extraneous-conductive-parts to reduce dangerous potential differences. Their purposes overlap in the overall safety design, but they are not interchangeable terms. The design must define the earthing arrangement and protective measures.
022. Establish the system earthing arrangement
Confirm whether the installation uses the specified TN, TT, IT or other project-defined arrangement. Identify the source neutral treatment, main earthing terminal, protective conductors, electrode system and any neutral earthing resistor. The arrangement affects fault-current paths, protective-device operation and verification requirements.
033. Main earthing terminal and bonding network
The main earthing terminal provides a central connection point for protective conductors and specified bonding conductors. Review the conductor schedule, connection details, labels, accessibility and corrosion protection. Metallic services and structural elements should be bonded only as required by the applicable design and rules; do not arbitrarily connect isolated systems.
044. Cable armour and equipment enclosures
Where cable armour or metallic screens are used as part of the protective or bonding arrangement, verify the approved termination method, glands, earth tags, bonding links and continuity. Confirm that the fault-current path and thermal withstand are addressed by design. Armour is not automatically an adequate protective conductor in every installation.
055. Electrode system and measurements
Earth electrode design may involve rods, grids, rings, foundations or other arrangements. Test method and acceptance criteria depend on the system, site conditions, project specification and authority requirements. A single resistance value should not be presented as a universal pass/fail limit for every installation.
066. Inspection and testing
Check conductor size and routing against approved drawings, mechanical protection, joints, termination tightness, corrosion protection, identification and accessibility. Continuity testing, electrode resistance testing and other verification should follow the approved test plan and instrument method. Record test configuration and environmental/site conditions.
077. Typical nonconformities
Examples include missing earth links, painted contact surfaces, loose terminations, unlabelled conductors, damaged earth bars, unapproved flexible links, missing bonding at removable sections and incomplete as-built records. The corrective action should identify the precise location and drawing reference.
088. Documentation
Retain approved earthing drawings, conductor schedules, calculations, inspection records, test reports, instrument calibration details, nonconformance closure and as-built changes. Coordinate with civil and mechanical teams where embedded electrodes, foundations or metallic services are involved.
09Continuity path review
Trace the protective conductor from each item of equipment back to the designated earthing terminal or network. Check removable doors, gland plates, skid sections and hinged panels where flexible bonding links may be needed. Verify the connection method is suitable for corrosion, vibration and fault duty. Paint, coatings and insulating washers must not unintentionally interrupt a required bond.
10Coordination with civil works
For buried grids, rods, foundation electrodes or embedded conductors, coordinate material, depth, separation, joints, inspection access and protection with civil drawings. Inspect concealed work before concrete placement or backfilling. Record locations and as-built dimensions so future excavation does not unknowingly damage the earthing network.
11Testing method matters
Select a measurement method appropriate to the electrode/system arrangement and site conditions. Parallel metallic paths, connected services and soil conditions can influence readings. The test report should state the method, instrument, test lead arrangement, disconnected/connected state, weather/soil conditions where relevant and the acceptance criterion source.
12Fault and touch-voltage context
Earth resistance alone does not describe every safety aspect. The design may need to consider earth-fault current, protective-device disconnection, touch and step voltage, conductor thermal withstand and equipotential bonding. These checks belong to the project earthing/protection design and should not be replaced by a single field resistance measurement.
13Quick field review checklist
Before accepting or closing the work
- Confirm system earthing arrangement and design basis
- Trace MET, PE and bonding conductors
- Verify conductor sizes and termination details
- Inspect armour/screen bonding where specified
- Use approved test methods and acceptance criteria
- Record results, calibration and as-built changes
14How to use this reference
Convert each relevant check into a project-specific inspection point. Identify the responsible person, approved reference, witness/hold point, acceptance criteria and required record. Where a requirement is not stated in the available project documents, raise a technical query rather than inventing a value or applying a generic limit.
Educational reference only. This page does not replace approved design calculations, manufacturer procedures, permit-to-work controls or statutory requirements.