How to write an electrical commissioning plan

What an electrical commissioning plan contains, a typical commissioning sequence, roles and responsibilities, and a printable checklist for projects.

6 min readUpdated 29 Nov 2026Department: Testing & Commissioning
Testing & Commissioning

A commissioning plan is the document that explains how a project will prove that its electrical systems work: what will be tested, in which order, by whom, with which documents, and how the results are accepted. A good plan prevents delays at the end of the project — when time is shortest.

Last checked: 29 November 2026. Always follow your approved project specification, the manufacturer's instructions and the applicable standard edition. Test voltages and acceptance values must come from those documents.

01What a commissioning plan contains

SectionWhat to include
1. ScopeSystems and equipment covered (MV network, substations, LV distribution, lighting, pump stations, SCADA)
2. OrganisationCommissioning manager, testing engineers, specialist subcontractors, consultant and client witnesses, with responsibilities
3. Standards & documentsSpecification clauses, applicable standards, approved drawings, ITPs, method statements, test sheet templates
4. SequenceSystem-by-system order and dependencies — for example earthing before switchgear, MV before LV
5. ScheduleCommissioning activities linked to the construction programme, with hold and witness points
6. SafetyPermit-to-work, isolation, energisation authority, barriers, emergency arrangements
7. InstrumentsList of test equipment with calibration validity
8. Acceptance & recordsAcceptance criteria, how results are reviewed, numbering of test certificates
9. Defects (punch list)How defects are recorded, categorised and closed before energisation and handover
10. Energisation planStep-by-step energisation with checks at each stage and approvals required
11. HandoverAs-built drawings, O&M manuals, training, spare parts and warranties

02A typical electrical commissioning sequence

  1. Earthing system and bonding.
  2. MV cables, joints and terminations.
  3. RMUs and MV switchgear, including protection.
  4. Transformers.
  5. Main LV switchboards, then sub-main boards.
  6. Final circuits, lighting and small power.
  7. Motor control centres, VFDs and pump stations.
  8. Control, interlocks, SCADA and integrated system tests.
  9. Energisation in stages, then performance and trial operation.

03Roles and responsibilities (RACI)

ActivityContractorConsultantClient / utility
Prepare plan, ITPs, test sheetsResponsibleReviews / approvesInformed
Carry out testsResponsibleWitnesses hold pointsWitnesses where required
Approve protection settingsAppliesApprovesApproves utility interface
Energisation authorityRequestsRecommendsAuthorises
Handover documentsResponsibleReviewsAccepts

04Printable commissioning plan checklist

  • ☐ Scope and system boundaries defined
  • ☐ Commissioning team and witnesses named
  • ☐ Applicable specification clauses and standards listed
  • ☐ ITPs approved with hold and witness points
  • ☐ Test sheets with acceptance criteria prepared
  • ☐ Test instruments calibrated and certificates filed
  • ☐ Sequence and dependencies agreed
  • ☐ Schedule linked to construction programme
  • ☐ Permit-to-work and isolation procedure agreed
  • ☐ Protection settings approved
  • ☐ Punch list process agreed
  • ☐ Energisation procedure and authority approved
  • ☐ Training and O&M handover planned

Use the free commissioning planner to build your sequence and track progress.

05Tips that save time at the end of a project

  • Start the plan early — at the latest when equipment submittals are approved.
  • Agree acceptance criteria before testing, not after a failed result.
  • Test and accept system by system, so energisation is not one big final event.
  • Keep one test-certificate register with status for every item.

FAQFrequently asked questions

Who prepares the commissioning plan?

Usually the contractor's commissioning manager prepares it, and the consultant or client reviews and approves it.

When should the commissioning plan be prepared?

Early in the project — ideally once the design and main equipment submittals are approved — so tests, witnesses and documents are planned before installation finishes.

What is the difference between a commissioning plan and an ITP?

The commissioning plan covers the whole process, organisation and sequence. An Inspection and Test Plan (ITP) lists the specific inspections and tests for one equipment type or activity, with hold and witness points.