A commissioning plan is the document that explains how a project will prove that its electrical systems work: what will be tested, in which order, by whom, with which documents, and how the results are accepted. A good plan prevents delays at the end of the project — when time is shortest.
Last checked: 29 November 2026. Always follow your approved project specification, the manufacturer's instructions and the applicable standard edition. Test voltages and acceptance values must come from those documents.
01What a commissioning plan contains
| Section | What to include |
|---|---|
| 1. Scope | Systems and equipment covered (MV network, substations, LV distribution, lighting, pump stations, SCADA) |
| 2. Organisation | Commissioning manager, testing engineers, specialist subcontractors, consultant and client witnesses, with responsibilities |
| 3. Standards & documents | Specification clauses, applicable standards, approved drawings, ITPs, method statements, test sheet templates |
| 4. Sequence | System-by-system order and dependencies — for example earthing before switchgear, MV before LV |
| 5. Schedule | Commissioning activities linked to the construction programme, with hold and witness points |
| 6. Safety | Permit-to-work, isolation, energisation authority, barriers, emergency arrangements |
| 7. Instruments | List of test equipment with calibration validity |
| 8. Acceptance & records | Acceptance criteria, how results are reviewed, numbering of test certificates |
| 9. Defects (punch list) | How defects are recorded, categorised and closed before energisation and handover |
| 10. Energisation plan | Step-by-step energisation with checks at each stage and approvals required |
| 11. Handover | As-built drawings, O&M manuals, training, spare parts and warranties |
02A typical electrical commissioning sequence
- Earthing system and bonding.
- MV cables, joints and terminations.
- RMUs and MV switchgear, including protection.
- Transformers.
- Main LV switchboards, then sub-main boards.
- Final circuits, lighting and small power.
- Motor control centres, VFDs and pump stations.
- Control, interlocks, SCADA and integrated system tests.
- Energisation in stages, then performance and trial operation.
03Roles and responsibilities (RACI)
| Activity | Contractor | Consultant | Client / utility |
|---|---|---|---|
| Prepare plan, ITPs, test sheets | Responsible | Reviews / approves | Informed |
| Carry out tests | Responsible | Witnesses hold points | Witnesses where required |
| Approve protection settings | Applies | Approves | Approves utility interface |
| Energisation authority | Requests | Recommends | Authorises |
| Handover documents | Responsible | Reviews | Accepts |
04Printable commissioning plan checklist
- ☐ Scope and system boundaries defined
- ☐ Commissioning team and witnesses named
- ☐ Applicable specification clauses and standards listed
- ☐ ITPs approved with hold and witness points
- ☐ Test sheets with acceptance criteria prepared
- ☐ Test instruments calibrated and certificates filed
- ☐ Sequence and dependencies agreed
- ☐ Schedule linked to construction programme
- ☐ Permit-to-work and isolation procedure agreed
- ☐ Protection settings approved
- ☐ Punch list process agreed
- ☐ Energisation procedure and authority approved
- ☐ Training and O&M handover planned
Use the free commissioning planner to build your sequence and track progress.
05Tips that save time at the end of a project
- Start the plan early — at the latest when equipment submittals are approved.
- Agree acceptance criteria before testing, not after a failed result.
- Test and accept system by system, so energisation is not one big final event.
- Keep one test-certificate register with status for every item.
FAQFrequently asked questions
Who prepares the commissioning plan?
Usually the contractor's commissioning manager prepares it, and the consultant or client reviews and approves it.
When should the commissioning plan be prepared?
Early in the project — ideally once the design and main equipment submittals are approved — so tests, witnesses and documents are planned before installation finishes.
What is the difference between a commissioning plan and an ITP?
The commissioning plan covers the whole process, organisation and sequence. An Inspection and Test Plan (ITP) lists the specific inspections and tests for one equipment type or activity, with hold and witness points.