Field checks for pole foundations, erection, wiring, luminaire installation and final testing. This guide provides a structured field and engineering review framework. Apply the sequence to the approved scope and record project-specific requirements separately.
01Foundation readiness
Check approved foundation detail, concrete strength release, anchor bolt template, projection, orientation, level and underground service clearance.
02Pole erection
Inspect pole ID, material, coating, access door, base plate, verticality, anchor nuts and structural condition. Use approved lifting and work-at-height controls.
03Electrical installation
Check cable entry, glands, loop-in/loop-out joints, terminations, phase identification, protective conductor and bonding to the pole body.
04Luminaire and controls
Verify luminaire model, wattage, optic, mounting orientation, driver settings where specified, photocell/timer and control wiring.
05Final checks
Complete continuity, insulation resistance and functional checks under approved procedures. Record pole ID, feeder circuit, test instrument, actual readings and defects.